North Carolina General Contractor License Exam (Building Contractor) Exam Prep
Free practice questions

Free NCGC-B Practice Questions

10 exam-style questions with answers and explanations, straight from our 1,030-question bank. Tap an answer to check yourself. When you're ready, take the scored version in the free practice test.

Start the free practice test → ★★★★★4.9/5 from 2,400+ candidates · No signup

The NCGC-B exam has 90 questions and runs 3 hours 20 minutes.

These 10 free NCGC-B questions are organized by exam domain, so you can see how each part of the North Carolina General Contractor License Exam (Building Contractor) blueprint is tested. Reveal the answer and explanation under each question.

Domain 1: Site Work 6.7% of exam

Question 1

A crew transfers elevation from a benchmark at 412.36 ft. The backsight is 5.44 ft, and the foresight on the excavated footing bottom is 7.18 ft. The footing plan calls for a bottom elevation of 410.50 ft. What does the reading show?

Show answer & explanation

Correct answer: C - The excavation is 0.12 ft high and needs additional cut

Domain 2: Concrete 14.4% of exam

Question 2

For 4,000-psi concrete, three consecutive strength tests-each already averaged from the required cylinders-are 4,050 psi, 3,920 psi, and 4,170 psi. Under the acceptance criteria for concrete with f'c not over 5,000 psi, how should the results be evaluated?

Show answer & explanation

Correct answer: A - Accept the series; its three-test average exceeds 4,000 psi, and no test is more than 500 psi low

Question 3

Before a footing pour, inspection finds the #5 bottom bars supported 2 inches above the soil. The approved detail requires the footing to be cast directly against earth. What should the superintendent require before placement?

Show answer & explanation

Correct answer: D - Adjust or replace the supports so the bars have 3 inches of bottom cover before placement

Domain 3: Masonry 6.7% of exam

Question 4

After wind-driven rain, staining appears at both jambs of a masonry opening. Through-wall flashing is present beneath the sill, but it stops flush at each jamb; the weeps remain open. Which detail is missing from the flashing installation?

Show answer & explanation

Correct answer: B - End dams turned up at both jambs

Domain 4: Metals 13.3% of exam

Question 5

A shop drawing shows a fillet-weld symbol below the reference line. "1/4" appears to the left, "4-8" to the right, and a flag is placed at the arrow/reference-line junction. What work is specified?

Show answer & explanation

Correct answer: B - A 1/4-inch fillet weld on the arrow side, 4 inches long at 8-inch pitch, made in the field

Question 6

During steel erection, the frame has been plumbed, but the joist bridging and final deck connections are incomplete. A delivery arrives with bundled deck scheduled to be landed on the joists. What is the superintendent's best direction?

Show answer & explanation

Correct answer: D - Do not land the bundles until required bridging, connections, and erection-plan conditions are in place

Domain 5: Carpentry 7.8% of exam

Question 7

A cathedral-ceiling addition uses opposing rafters, but there are no ceiling joists or low rafter ties to resist outward thrust. The design provides vertical support at the ridge and posts to the foundation. Which member is carrying the roof load at the ridge?

Show answer & explanation

Correct answer: A - A structural ridge beam transferring load to the posts

Domain 6: Roofing 6.7% of exam

Question 8

Interior staining recurs at the lower end of a sloped roof where it terminates against a taller wall. Step flashing farther upslope is correctly lapped, but runoff is disappearing behind the wall cladding near the gutter. Which detail is most likely missing?

Show answer & explanation

Correct answer: C - Kickout flashing

Domain 7: Associated Trades 3.3% of exam

Question 9

A subcontractor proposes to seal a 2-inch insulated copper-pipe penetration through a 2-hour shaft wall with a listed system tested only for bare steel pipe. What should the general contractor require before the wall is closed?

Show answer & explanation

Correct answer: D - Use a listed system matching the wall, copper pipe, insulation, annular space, and required rating

Domain 8: Business and Law 7.8% of exam

Question 10

At a site meeting, the architect verbally directs a partition relocation that the contractor expects will increase both cost and duration. The work is not needed to address an emergency. Which response best protects the contractor without unnecessarily stopping the project?

Show answer & explanation

Correct answer: A - Give prompt written notice, seek written change authorization, document cost and time separately, and continue unaffected work

The rest of the NCGC-B blueprint

The NCGC-B exam also covers these domains. Drill them in the full free practice test:

That's 10 of 1,030

The full bank has 1,020 more NCGC-B questions with explanations.

Continue in the free practice test →

View plans